單項(xiàng)選擇題
項(xiàng)目被估算的成本是$1.5百萬(wàn),進(jìn)度維持六個(gè)月時(shí)間,在三個(gè)月之后,掙值分析顯示下面情況:EV=$650,000.PV=$750,000.AC=$800,000,進(jìn)度和成本偏差各是多少?()
A.SV=+$100,000/CV=+$150,000
B.SV=+$150,000/CV=―$100,000
C.SV=―$50,000/CV=+$150,000
D.SV=―$100,000/CV=―$150,000