A customer needs a 2-way Xeon system today but plans on expanding to a 4-way early next year.  The customer is looking to limit the initial costs as much as possible but may not be as budget constrained next year.  Which of the following is the best solution to all the customer’s needs?()

A.An x445 with 2 Xeon DP processors.  Plan on adding 2 more Xeon DP processors next year.
B.An x445 with 2 Xeon MP processors.  Plan on adding 2 more Xeon MP processors next year.
C.An x366 with 2 Xeon MP processors.  Plan on adding 2 more Xeon MP processors next year.
D.An x366 with 2 Xeon DP processors.  Plan on adding 2 more Xeon DP processors next year.